Indices of the value of construction put in place, Slovenia, July 2020

The value of construction put in place 12.3% higher than in June 2020 and 1.9% lower than in July 2019

The value of construction put in place in July 2020 was 12.3% higher than in the previous month and 1.9% lower than a year ago.

  • 9/15/2020
  • |
  • provisional data

The value of construction put in place in July 2020 higher than in the previous month 

In comparison with June 2020, the value of construction put in place in July 2020 increased by 12.3%. This time the value of construction put in place increased compared to the previous month after it had been decreasing during the previous four months. In July 2020, the value of construction put in place on buildings increased at the monthly level by 12.1%; on residential buildings it went up by 9.2% and on non-residential buildings by 15.5%. The value of construction put in place on civil engineering increased by 13.0%. 

The value of construction put in place in July 2020 lower than in July 2019
 

In comparison with July 2019, the value of construction put in place in July 2020 decreased by 1.9%. At the annual level it decreased for the fifth consecutive time (in May 2020 it was lower by 13.3% and in June 2020 by 15.8%). As regards buildings it went up by 7.9%, while as regards civil engineering it went down by 5.8%. At the annual level the rise in the value of construction put in place on buildings was the result of the higher value of construction put in place both on residential buildings (by 17.2%) and on non-residential buildings (by 4.6%). 

The value of construction put in place in the first seven months of 2020 lower than in the same period of 2019


The value of construction put in place in the first seven months of 2020 decreased by 5.0% compared to the same period of the previous year. As regards buildings it went down by 6.3% and as regards civil engineering by 4.5%.

Real indices of the value of construction put in place, Slovenia (Ø2015=100)
Real indices of the value of construction put in place, Slovenia (&Oslash2015=100)
1) In the trend-cycle component the most recent data are unreliable (the end-point problem).
Source: SURS
Real indices of the value of construction put in place, Slovenia
VII 2020
VI 2020 
VII 2020
VII 2019
I–VII 2020
I–VII 2019
VII 2020
 Ø 2015 
Construction112.398.195.0115.6
  buildings112.1107.993.7150.0
  civil engineering113.0 M94.2 M95.5 M104.4 M
M less reliable estimate – use with caution
Source: SURS
METHODOLOGICAL NOTE

Data are seasonally adjusted.
Data for the last 3 months are provisional. With each release the data for the last 3 months can be corrected and supplemented with new data.